Tunnels are underground passageways, dug through the surrounding soil and enclosed except for an entrance and an exit at each end. As bridges, they are essential for a well-functioning transport network. In urban areas, they are usually built at locations with limited space at the surface.

Underpasses are very similar structures, except that they are usually shorter. Underpasses improve traffic flow in traffic intense intersections at the street level, sometimes in combination with bridges. Underpasses are generally designed as a rehabilitation of a crossroad, and hence speed of execution is of utmost importance.

Hot rolled steel sheet piles are ideal for tunnel and underpass construction, due to:
  • faster execution time,
  • reduced surface disruption, as no over excavation for foundations is required,
  • sheet piles have immediate load-bearing capacity,
  • steel sheet piles can be easily made aesthetically attractive,
  • guaranteed imperviousness through the use of sealing products or welded interlocks,
  • excellent fire resistance performance with and without protection.
Several construction methods can be used for the execution of tunnels and underpasses depending on the soil conditions and other technical requirements. Shallow structures are often constructed using the cut-and-cover method. This construction method consists on the excavation of a trench that is subsequently roofed over with an overhead support system strong enough to support the loads coming from above.

An alternative method is the top-down method, where the soil is dug below the top slab, which is executed right after installation of the sheet pile structure. In this configuration, traffic disruption at street level can be reduced drastically. The main drawback is a slightly longer excavation phase, but it does not disturb traffic nor reduce the benefits of this method.

Challenges for the designer are fire resistance and watertightness. ArcelorMittal developed in collaboration with the University of Liège in Belgium a design method and a software that can simulate the behaviour of a steel sheet pile wall under high temperature in different soil conditions. One of the parameters is the temperature evolution on the atmospheric side, which depends highly on the fire approach (ISO curves or natural fire). For more information, see our brochure “Underground car parks: Fire resistance”.
Last modified: January 7, 2022
Related links
Downloads
CS - BE | Railway underpass – Lokeren | 2018 Railway underpass in Lokeren, BE – 390 t [...]
Read more
CS - DK | Highspeed railway line Copenhagen-Ringsted-TP4 | Copenhagen | 2014
Read more
Liefkenshoek rail link Antwerp, Belgium
Read more
Underground car parks | Fire resistance
Read more